Bauer completes Indonesian airport geotech scheme

Bauer has announced that it has successfully completed ground improvement work for a new taxiway at Soekarno-Hatta International Airport in Jakarta, Indonesia.

Completion of the work clears the way for construction of a new link between link within the airport’s eastern airfield to allow it to meet rising passenger demand.

Bauer Pratama Indonesia carried out the work on the East Connection Taxiway Phase 1 project for main contractor Hutama Karya and followed on from a scheme for a secondary apron previously delivered by the partnership.

Bauer undertook full displacement columns to depths of between 5m and 16m across a 199,000m2 area and installed 1,072 1.2m diameter rotary bored piles to depths of up to 37m for taxiway bridges.

The ground engineering work was completed in eight months.

Want to read more? Subscribe to GE’s enewsletters and follow us on Twitter and LinkedIn